According to the data and stats that were collected, 'The Scott Pad' channel has a poor rank. The feed was last updated more than a year ago. In addition 'The Scott Pad' includes a significant share of images in comparison to the text content. The channel mostly uses long articles along with sentence constructions of the basic readability level, which is a result indicating a well-balanced textual content on the channel.

About 'The Scott Pad' Channel

Building Our Dream Home!

? Updates History Monthly Yearly
? Content Ratio
? Average Article Length

Medium-length materials prevail on 'The Scott Pad' that may be an effective tactic to grip their readers’ attention with a wider range of helpful content. There are also longer items making up more than one third of all articles, which can provide a deeper insight into their subjects. Moreover, there are a few short articles.

short

long

? Readability Level

'The Scott Pad' mostly contains texts of a basic readability level which may show their aim to reach a wider audience. Besides, there are articles of intermediate readability, which make up more than one third of all content on the channel.

advanced

basic

? Sentiment Analysis

Positive emotional expressions prevail throughout the texts: they may include favorable reviews, appreciation or praise in regard to the subjects addressed on the channel. However, the channel also contains some rather negative or critical records that make up just a small amount of all its content.

positive

negative

Recent News

Unfortunately The Scott Pad has no news yet.

But you may check out related channels listed below.

Week 22 Schedule

[...] , finished most of the front handrail, repaired the rear deck post, got much of the bio-retention pond completed, got electricity to the house, finished the electrical work, finished the carpet [...]

Week 20 Schedule

[...] all the registers. Carpet Installation: On Friday, we expect to have our carpet installed. Bio-Retention Pond: By Friday, we hope to have our bio-retention pond completed (finally!). Final Grading: If [...]

Week 21 Schedule

[...] porch columns built and got our shutters installed. And on the exterior, we didn’t get the bio-retention pond in nor the final grading. The coming week will be all about tying up some interior loose [...]

Week 23 Schedule

[...] and finish seeding/strawing the yard in order to pass our final. We also finished our bio-retention pond last week…though our stormwater management inspector gave us approval to hold off planting [...]

Week 18 Schedule

[...] installed (one needs to wait until front porch is completed). We didn’t get our foundation work completed and we also didn’t measure for countertops, two relatively important items. [...]

Week 4: Schedule

[...] My original schedule called for us to be through foundation work and starting on framing by today, but I underestimated the complexity and sheer volume of [...]

Week 3: Schedule

[...] should pretty much put us back on schedule. During Week #3, the plan is to keep moving on foundation work. The schedule calls for foundation to finish by the end of week #3, but we’re going to lose [...]

Week 19 Schedule

[...] , we got the new footer poured for the back deck (the one that was missed during foundation work) and got a new front step poured to finish our front porch. We still have a decent [...]

Trim Bid – Builders First Source

[...] After seeing how well our framing crew from Builders First Source did (both quickly and high quality work), I decided that I really wanted to use them for [...]

Fab Friday Photos- Week 8

[...] for greeting the garbage trucks, building block towers, and sipping sangria!) Builders First Source will be back starting tomorrow, full speed ahead, to take care of punch list items [...]

Fab Friday Photos- Week 10

[...] as needed, and a few interior walls we’d requested for soundproofing. Simultaneously, Builders First Source was back on site installing the screened-in porch; and earlier this (Friday) morning, the [...]

Sneak Preview Inside!

Interior framing is complete- With the help of an outstanding crew at Builder’s First Source, we were even able to make a few changes on the fly! St [...]

Watch on Wednesday: Week 8

Watch on Wednesday: Week 8 This Week’s Location: In the bathtub. GET YOUR MIND OUT OF THE GUTTER, PEOPLE! Tub’s sitting in the garage, not even i [...]

Watch on Wednesday: Week 9

Watch on Wednesday: Week 9 This Week’s Location: Near the staircase that floods the house with sunshine, not in the monsoon that flooded the yard y [...]

Watch on Wednesday: Week 11

Watch on Wednesday: Week 11 This Week’s Location: In the basement. The dark, quiet, scary basement… which is drywalled and AWESOME! Bill Werking [...]

Watch on Wednesday: Week 13

Watch on Wednesday: Week 13 This Week’s Location: Sitting amidst a sea of freshly-installed HARDWOOD FLOORS! (i.e. hands-down, my absolute most FAV [...]

?Key Phrases
Week 22 Schedule

[...] , finished most of the front handrail, repaired the rear deck post, got much of the bio-retention pond completed, got electricity to the house, finished the electrical work, finished the carpet [...]

Week 20 Schedule

[...] all the registers. Carpet Installation: On Friday, we expect to have our carpet installed. Bio-Retention Pond: By Friday, we hope to have our bio-retention pond completed (finally!). Final Grading: If [...]

Week 21 Schedule

[...] porch columns built and got our shutters installed. And on the exterior, we didn’t get the bio-retention pond in nor the final grading. The coming week will be all about tying up some interior loose [...]

Week 23 Schedule

[...] and finish seeding/strawing the yard in order to pass our final. We also finished our bio-retention pond last week…though our stormwater management inspector gave us approval to hold off planting [...]